Time and Work questions for competitive exams: rules, worked examples and practice

Time and work questions find how long people take to finish a job together. Work with the part of the job done per day.

Key rules and formulas

Common traps

Where Time and Work is asked

Worked examples

Example 1

A can finish a work in 24 days and B can finish it in 12 days. In how many days will they finish it working together?

  1. 4 days
  2. 8 days
  3. 10 days
  4. 2 days

Answer: B) 8 days

Together per day: 1/24 + 1/12 = 1/8, so time = 8 days.

Open this question

Example 2

A can finish a work in 15 days and B can finish it in 10 days. In how many days will they finish it working together?

  1. 12 days
  2. 8 days
  3. 2 days
  4. 6 days

Answer: D) 6 days

Together per day: 1/15 + 1/10 = 1/6, so time = 6 days.

Open this question

Example 3

A can finish a work in 20 days and B can finish it in 30 days. In how many days will they finish it working together?

  1. 10 days
  2. 18 days
  3. 16 days
  4. 12 days

Answer: D) 12 days

Together per day: 1/20 + 1/30 = 1/12, so time = 12 days.

Open this question

Frequently asked questions

What is Time and Work in competitive exams?

Time and work questions find how long people take to finish a job together. Work with the part of the job done per day.

Which exams ask Time and Work questions?

On MockBazaar, Time and Work questions appear in IBPS Clerk Prelims, IBPS PO Prelims, RRB Group D, SBI Clerk Prelims, SBI PO Prelims, SSC CGL Tier 1, SSC CGL Tier 2.

What is the most common mistake in Time and Work?

Adding the days instead of the daily rates.